PMP Mock Exam Bank: 50 Popular Situational Questions with Answer Analysis (Free Practice)

Want to pass the PMP exam in one go? We provide selected PMP mock questions (People & Agile Domains) with detailed expert analysis. Master PMI question logic and exam techniques, and start your free practice now to prepare for your PMP Exam!

PMP Mock Exam Bank: 50 Popular Situational Questions with Answer Analysis (Free Practice)

As the saying goes, "Knowledge without practice is useless." For candidates preparing for the PMP Exam (Project Management Professional certification), this is an absolute golden rule. Many candidates can recite the "PMBOK Guide" by heart but still feel helpless when facing actual exam questions. Why? Because the current PMP exam is no longer a simple memory test of knowledge points; it is a deep assessment of the "Project Management Mindset."

Can you make the judgment most consistent with PMI values for 180 situational questions within a high-pressure 230-minute window? This requires a lot of practical exercise. To help everyone break through the dilemma of "understanding theory but getting questions wrong," KORNERSTONE has specially compiled this selection of PMP mock questions with detailed analysis. We focus on the "People" and "Agile" domains, which currently have the highest weight in the exam, to help you master the correct problem-solving logic from the ground up.

PMP Exam Situational Questions: People Domain

According to the latest Examination Content Outline (ECO), the People domain accounts for 42% of the total score. these questions mainly test how you, as a Project Manager (PM), use soft skills to resolve conflicts, lead teams, and manage stakeholders. Remember, PMI advocates for "Servant Leadership." When choosing answers, please prioritize collaboration, empowerment, and support.

Question 1: Conflict Management

Scenario: During the execution phase of a critical project, two senior technical experts have a heated argument over which database architecture to adopt. This dispute has lasted for two days, seriously affecting team morale and project progress. As the project manager, what action should you take?

  1. Decide to adopt the proposal of one of the experts so the team can continue working.
  2. Escalate the issue to the functional manager and ask them to make the technical decision.
  3. Arrange a meeting for both parties to list the pros and cons of their respective proposals and guide them toward a consensus.
  4. Separate the two experts and have them manage different modules of the project to avoid conflict.
Click to view answer and analysis

Correct Answer: C

Expert Analysis:

This question tests the conflict resolution technique of "Collaborate/Problem Solve."

  • Why choose C? This is the ideal solution. When facing professional differences that affect progress, a PM should facilitate dialogue and seek a win-win. By objectively analyzing pros and cons, you not only solve the current technical problem but also maintain team relationships.
  • Why not A (Force/Direct)? While it solves the problem quickly, it creates a "win-lose" situation, damaging the motivation of the party whose idea was not adopted. Furthermore, the PM may not have the technical expertise to make this decision.
  • Why not B (Escalate)? Technical conflicts within the project should first be resolved by the team. Premature escalation shows a lack of problem-solving ability in the PM.
  • Why not D (Withdraw/Avoid)? This only temporarily hides the problem and does not resolve the core architectural disagreement, which could lead to system integration failure in the long run.

Question 2: Team Performance and Motivation

Scenario: You are leading a high-pressure software development project. Recently, you noticed low team morale and several missed minor deadlines. During a retrospective meeting, members complain that the workload is too heavy and they feel a lack of support from management. What should you do next?

  1. Remind the team of the importance of project deadlines and ask them to work overtime to catch up.
  2. Review the Backlog with the team, re-prioritize items, and remove low-value tasks.
  3. Apply for bonuses from the HR department to motivate the team to complete the remaining work.
  4. Hire more temporary staff to share the workload.
Click to view answer and analysis

Correct Answer: B

Expert Analysis:

This question embodies the core of Servant Leadership: removing obstacles and supporting the team.

  • Why choose B? When a team is overloaded, the PM's responsibility is to protect the team and ensure a sustainable workload. By re-evaluating priorities and focusing on high-value work, the PM can alleviate pressure while ensuring the delivery of core project value.
  • Why not A? This is typical "command and control" management. Pressuring a team with low morale only leads to burnout and higher turnover rates.
  • Why not C? According to Herzberg's Two-Factor Theory, money is often a hygiene factor rather than a long-term motivator. If the working environment and pressure issues aren't addressed, bonuses won't help.
  • Why not D? According to Brooks' Law, adding manpower to a late software project often makes it even later due to increased communication overhead.

Question 3: Virtual Team Management

Scenario: Your project team is distributed across three different time zones. In recent online status meetings, you noticed that some members have very low engagement, and some are even handling other emails during the meeting. To improve this situation, what should you do first?

  1. Establish strict meeting rules requiring everyone to turn on their cameras and prohibiting multitasking.
  2. Work with the team to develop a Team Charter to agree on communication norms and meeting etiquette.
  3. Switch to sending email reports and cancel synchronous meetings to save everyone time.
  4. Privately criticize those inattentive members and record it in their performance reviews.
Click to view answer and analysis

Correct Answer: B

Expert Analysis:

  • Why choose B? In the PMP exam, whenever a question involves team norms, the "Team Charter" is almost always the standard answer. Letting the team "co-create" the rules increases their commitment and sense of belonging.
  • Why not A? Unilaterally imposing rules (Dictate) by the PM violates the principles of self-organizing teams and can easily cause resentment.
  • Why not C? Virtual teams already lack interaction; completely canceling synchronous meetings will further weaken team cohesion.
  • Why not D? Punitive measures should be a last resort. One should first try to guide behavior by building consensus.

Agile Management Sample Questions

As Agile and Hybrid projects now account for 50% of the exam, you must be familiar with the basic operations of frameworks like Scrum and Kanban, as well as the "Value-Driven" and "Adaptability" mindsets of Agile.

Question 4: Sprint Planning and Scope Change

Scenario: The team is in the middle of a two-week Sprint, currently on Day 5. The Product Owner rushes into the office, requesting the immediate addition of a "very urgent" new feature, stating it is critical to the customer. As an Agile Project Manager (or Scrum Master), how should you respond?

  1. Immediately have the team stop their current work to prioritize developing this new feature.
  2. Tell the Product Owner that the Sprint scope is locked and cannot be changed, and ask them to wait until the next Sprint.
  3. Communicate with the Product Owner; if the feature is indeed urgent, add it to the Backlog and consider removing other tasks of equivalent effort from the current Sprint, or save it for the next Sprint planning.
  4. Require the Product Owner to submit a formal Change Request and hold a CCB meeting for approval.
Click to view answer and analysis

Correct Answer: C

Expert Analysis:

  • Why choose C? Agile embraces change but also protects team stability. Option C reflects negotiation and trade-offs. If something must be added, something of equal size must be swapped out to keep the Sprint workload constant and avoid team burnout.
  • Why not A? This destroys the integrity of the Sprint (Sprint Goal) and causes the team to frequently switch contexts, lowering efficiency.
  • Why not B? Although it is recommended to lock the Sprint, refusing to communicate entirely contradicts the Agile value of "Customer collaboration over contract negotiation."
  • Why not D? This is a traditional Waterfall approach. In Agile, the Product Owner manages the priority of the Backlog and does not need to go through a rigid CCB process.

Question 5: Retrospective Meeting

Scenario: In recent Sprint Retrospectives, team members have only been blaming each other, the atmosphere is tense, and no concrete improvement plans have been produced. As a Scrum Master, how should you intervene?

  1. Record everyone's complaints and report the team's unprofessional behavior to senior management.
  2. Suspend the Retrospective meetings until the team members learn how to communicate politely.
  3. Guide the team to revisit the "Prime Directive," build psychological safety, and use specific facilitation techniques (like a Fishbone diagram) to focus on process improvement rather than blaming individuals.
  4. Personally develop an improvement plan and oversee the team's execution in the next Sprint.
Click to view answer and analysis

Correct Answer: C

Expert Analysis:

  • Why choose C? Retrospectives usually fail due to a lack of psychological safety. Norm Kerth's Prime Directive emphasizes: "Regardless of what we discover, we must understand and truly believe that everyone did the best job they could, given what they knew at the time..." The facilitator needs to pull the discussion back to "process issues" rather than "people issues."
  • Why not A? "Snitching" will completely destroy the team's trust in the Scrum Master.
  • Why not B? Avoiding the problem is not a solution. The Retrospective is the core mechanism of Agile improvement and cannot be easily canceled.
  • Why not D? Improvement plans must be "owned by the team"; otherwise, they will not have the motivation to execute them.

Incorrect Question Analysis Tips: How to Read PMI's "Subtext"

After finishing these PMP sample questions, you might find that your choices differ from the "standard answers." This is normal! Often, we choose incorrectly because we use "real-world experience" instead of "PMI's ideal-world logic." Here are three tips to quickly adjust your thinking:

1. Distinguish "Immediate Action" from "Analysis First"

In reality, if a boss raises a problem this second, you might implement a solution the next. But in the PMP exam, this is usually wrong. PMI's logic is: Analyze -> Formulate Plan -> Execute.
Tip: When a question asks "what to do next," look for options containing words like "analyze impact," "review plan," or "assess" first.

2. Beware of "Passing the Monkey"

Any option that involves "reporting the problem to the sponsor," "pushing it to the functional manager," or "asking the client to solve it themselves" is 90% likely to be a distractor. PMI assumes you are a capable, proactive project manager. You should try to solve the problem within your own authority unless it exceeds the boundaries defined in the Project Charter.

3. Process vs. People

In traditional Waterfall questions, strictly following the process (like change control) is often correct; but in Agile questions, "Individuals and interactions" are valued over processes. If the options are "Follow the process but offend the client/team" versus "Adjust flexibly to meet value," the latter is usually chosen in Agile questions.

Feel like 5 questions aren't enough?

The PMP exam question bank is vast, and relying on scattered practice makes it difficult to cover all knowledge points. True preparation requires a systematic PMP Mock Exam system that is fully aligned with the latest ECO outline.

KORNERSTONE PMP Certification Course provides students with:

  • Full Realistic Mock Exam Bank: Over 1,000 selected questions covering predictive, agile, and hybrid scenarios.
  • Intelligent Error Analysis: The system automatically tracks your weak areas (Is it Cost Management? Or unclear Agile concepts?), helping you strengthen them precisely.
  • Pre-exam Cram Session: Led by senior instructors to dismantle high-difficulty questions on-site and teach exclusive "elimination methods" and "keyword positioning" techniques.

Don't let your registration fee go to waste. Choose a professional preparation partner to ensure your PMP journey is a success on the first try!

Register now to access the full question bank and exam strategies